The installation method of HDPE reinforced spiral corrugated pipe mainly includes the following steps, which ensure the quality and safety of pipeline connection.

 

1、 Preparation for Installing HDPE Reinforced Spiral Corrugated Pipe   

 

Inspection of pipes and fittings: Before installation, a comprehensive inspection of HDPE reinforced spiral corrugated pipe and their fittings should be carried out to ensure that the pipes are free of defects such as damage, cracks, and deformation, and that the fittings are complete and of qualified quality.

 

Measurement and cutting: Accurately measure the length of the pipeline according to design requirements and actual site conditions, and use specialized tools for cutting. When cutting, pay attention to the flatness of the incision to avoid damaging the inner wall of the pipeline.

 

Cleaning and polishing: Clean the cut and connection parts of the pipeline, remove impurities and burrs. For pipelines that require hot melt or electric melt connections, the connection parts also need to be polished to improve the connection quality.

 

2、 Selection of Connection Methods for HDPE Reinforced Spiral Corrugated Pipe   

 

Select the appropriate connection method based on factors such as pipeline diameter, working pressure, medium properties, and site conditions. Common connection methods include hot melt connection, electric melt connection, heat shrink sleeve connection, clamp encrypted sealing tape connection, and extrusion melt welding.

 

3、 Installation Steps of HDPE Reinforced Spiral Corrugated Pipe     

 

Taking the heat shrink sleeve connection as an example, the specific installation steps are as follows:

Check the mating end face: Ensure that the mating end faces of the two steel strip pipes to be connected are flat, and the local gap after closure is less than 6 millimeters. If it does not meet the requirements, on-site adjustments are required.

 

Overhead pipeline: Elevate the ends of two steel strip pipes to be connected, so that they are at a certain distance from the ground or ditch wall, in order to facilitate the operation of heating tools in the circumferential direction.

 

Insert heat shrink sleeve: Thread the heat shrink tube onto one end of the two pipes to be connected, and pull it to a position greater than 500 millimeters from the connection end face. Pay attention to protecting the protective paper layer on the inner wall of the heat shrink tube from damage.

 

Polishing the end face: Use a wire brush to polish the cylindrical surface layer about 120 millimeters long on the mating end face of the pipe to be connected, and the peaks and valleys should be roughened. At least polish the length of three and a half nodes to ensure the quality of the connection.

 

Cleaning and fixing: Use a clean cloth to wipe off the polished pipe end, align and fix the two pairs of connecting pipe end faces, without any misalignment.

Preheating and connection: Preheat the circumferential surfaces of the two pipe ends (three wave distances from the mating end face) with a red flame to achieve a surface temperature of 40 to 50 degrees. Then, wrap and bake the reinforced fiber heat shrink sleeve at the connection point, requiring it to wrap around the circumference for at least one circle and overlap firmly. Preheat the two ends of the connecting pipe to within the polishing line, so that the surface temperature reaches at least 15 degrees below the softening temperature of the hot melt adhesive.

 

4、 Quality Inspection and Acceptance After Installation of HDPE Reinforced Spiral Corrugated Pipe      

 

After installation, a comprehensive inspection of the quality of HDPE reinforced spiral corrugated pipe  connections should be conducted. The inspection includes checking whether the connection parts are firm, whether the sealing is good, whether the pipeline is straight, etc. Problems should be promptly addressed and reconnected. At the same time, water pressure tests or regular gas maintenance and tightness checks are also required. The content of the test inspection includes checking whether the pipeline works properly, ensuring that the pipeline deformation system is installed, meeting the connection design requirements, and whether the use requires looseness or leakage.

 

In summary, the installation method of HDPE reinforced spiral corrugated pipe includes preliminary preparation, selection of connection method, installation steps, quality inspection and acceptance, and subsequent maintenance. In practical operation, relevant specifications and requirements should be strictly followed to ensure the quality and safety of the pipeline system.

 

As a company specializes in plastic products, our business scope is very broad . We have PVC sheet, PVC panel , CPVC sheet , PP sheet, HDPE sheet , PVC rod , PVC pipe , HDPE pipe һәм welding rod .About the HDPE pipe, we have different type of it .Such as HDPE water supply pipe,HDPE double wall corrugated pipe һәм HDPE reinforced spiral corrugated pipe. The HDPE reinforced spiral corrugated pipe price in our company are reasonable . If you are interesting in our product welcome to contact us!